NEW QUESTION # 47
In which process does the system automatically select the source of supply, reserve supply until fulfillment and ship to the customer?
- A. Back-to-Back
- B. Consigned Inventory
- C. Internal Material Transfer
- D. Drop Shipment
Answer: A
NEW QUESTION # 48
Your customer manages all the procurement and warehouse operations in the US and has decided to create a US business unit for this purpose. Identify two mandatory pieces of information required to create a US business unit.
- A. Default Set (*)
- B. Buyer
- C. Secondary Ledger
- D. Business Function (*)
- E. Manager
Answer: A,D
NEW QUESTION # 49
Which two enterprise structures can be used to build the management structure of an organization in Oracle Fusion Applications?
- A. Business Unit
- B. Cost Center
- C. Division
- D. Department
- E. Legal Entity
Answer: A,C
NEW QUESTION # 50
Which three sort criteria are available to pick material for a movement request?
- A. Serial
- B. Lot (*)
- C. Subinventory (*)
- D. Revision (*)
Answer: B,C,D
NEW QUESTION # 51
During your implementation, you are required to do a setup to move items from one locator to another locator in the same inventory organization.
Which two types of inventory transactions are required to accomplish this?
- A. Move Request
- B. WIP Component Issue
- C. Subinventory Transfer
- D. Locator Transfer
- E. Miscellaneous Receipt
Answer: A,C
Explanation:
Advanced Inventory Transactions
NEW QUESTION # 52
Back-to-Back Supply Creation On-Hand Flow
The back-to-back on-hand available (ATP) flow is the simplest in terms of the number of steps that constitute the flow. This flow occurs where on hand supply is available in the fulfillment warehouse for the ordered back-to-back item at the time of order promising. Because on-hand goods already exist in the form of on hand, Oracle Supply Chain Orchestration directly sends a request to reserve the on hand quantity against the back-to-back sales order. You can ship the sales order immediately after the reservation is created.
The following figure shows the back-to-back supply creation on-hand flow.
Answer:
Explanation:
See the Explanation for the complete solution.
Explanation:
Back-to-Back Supply Creation: On-Hand Flow in Oracle Cloud
1. Overview of Back-to-Back On-Hand Flow
The Back-to-Back On-Hand Flow is the simplest and fastest fulfillment method in Oracle Cloud because the required stock is already available in the fulfillment warehouse at the time of sales order entry.
Unlike Buy, Make, or Transfer Flows, no additional supply is created. Instead, Oracle Supply Chain Orchestration (SCO) directly reserves the available inventory against the sales order, making it ready for immediate shipment.
2. Step-by-Step Back-to-Back On-Hand Flow Process
Below is a detailed step-by-step breakdown of the Back-to-Back On-Hand Flow using Oracle Fusion Cloud applications.
Step 1: Enter & Schedule Sales Order
* The customer places a sales order in Oracle Order Management.
* The system checks inventory availability in Oracle Inventory Cloud.
* Oracle Global Order Promising (GOP) determines that the required stock is already available in the fulfillment warehouse.
* No procurement, manufacturing, or warehouse transfers are needed.
* The sales order is scheduled immediately for fulfillment.
# System Action: The system identifies that on-hand stock is available and proceeds to reservation.
Step 2: Reserve Available Inventory
* Oracle Supply Chain Orchestration (SCO) reserves the available stock against the back-to-back sales order.
* The system ensures that this stock is allocated only to this order, preventing other orders from using it.
# System Action: The system reserves the required quantity for the sales order.
Step 3: Ship the Sales Order
* The order moves directly to shipping in Oracle Inventory Cloud.
* The warehouse team picks, packs, and ships the goods using Oracle Shipping Execution.
* An invoice is generated in Oracle Receivables.
* The sales order is closed after shipment.
# Final Action: The system completes the order and ships it to the customer.
3. Oracle Fusion Cloud Modules Involved in On-Hand Flow
A screenshot of a computer AI-generated content may be incorrect.
4. Benefits of Back-to-Back On-Hand Flow
# Fastest Fulfillment Process - No need for procurement, manufacturing, or transfers.# Minimizes Order Processing Time - Orders can be shipped immediately after reservation.# Eliminates Additional Costs - No purchase orders, work orders, or transfers required.# Ensures Inventory Optimization - Uses available stock efficiently.# Improves Customer Satisfaction - Quick shipping and fulfillment.
5. Real-World Use Case
Scenario: Electronics Retailer Fulfilling a Popular Smartphone Order
A retailer sells Smartphone XYZ and has 100 units in stock at its fulfillment warehouse.
Process Flow:
* A customer places an order for 10 units of Smartphone XYZ.
* Oracle Global Order Promising (GOP) identifies that stock is available.
* Oracle Supply Chain Orchestration (SCO) reserves 10 units against the sales order.
* The warehouse team picks, packs, and ships the smartphones.
* The customer receives the order, and the system closes the sales order.
# Result: The order is fulfilled immediately without additional supply creation.
NEW QUESTION # 53
Back-to-Back Supply Creation Make Flow
The supply document for a back-to-back make flow is a work order. As soon as the work order is created in Oracle Fusion Cloud Manufacturing, it's tied to the back-to-back sales order in the form of a reservation in inventory. The work order goes through the regular production process and the work order completion transaction issues finished goods to inventory.
Note: Back-to-back flow is currently supported for only discrete manufacturing.
The following figure shows the back-to-back supply creation make flow.
Back-to-Back Supply Creation Transfer Flow
The supply document for a back-to-back transfer flow is a transfer order. The transfer order is created in inventory and reserved against the back-to-back sales order. When the transfer order is ready to be fulfilled, an interorganization shipment moves goods from the source organization to the destination organization. An interorganization receipt in the destination organization (which is also the fulfillment warehouse on the back- to-back sales order) creates on hand to fulfill the sales order.
The following figure shows the back-to-back supply creation transfer flow.
Answer:
Explanation:
See the Explanation for the complete solution.
Explanation:
Back-to-Back Supply Creation Flows: Make & Transfer in Oracle Cloud
1. Overview of Back-to-Back Supply Creation Flows
Back-to-back (B2B) supply creation flows in Oracle Fusion Cloud allow businesses to generate supply only when a sales order is placed. The system creates supply documents dynamically based on sourcing rules and executes supply fulfillment through Manufacturing (Make Flow) or Inventory Transfer (Transfer Flow).
Each flow follows these key steps:
* Sales Order Entry & Scheduling - A customer places an order that requires supply creation.
* Supply Order Generation - The system determines whether to manufacture or transfer stock.
* Supply Execution - The supply is produced (Make Flow) or transferred from another warehouse (Transfer Flow).
* Receiving & Reservation - The supply is received and linked to the sales order.
* Order Fulfillment - The sales order is shipped to the customer.
2. Back-to-Back Supply Creation: Make Flow (Manufacturing-Based Fulfillment) The Make Flow is used when the item must be manufactured in-house because it is not available in stock or through procurement. The system creates a Work Order (WO) in Oracle Manufacturing Cloud and ties it to the sales order.
Step-by-Step Make Flow Process
Below is the step-by-step breakdown of the Back-to-Back Make Flow using Oracle Fusion Cloud applications.
Step 1: Enter & Schedule Sales Order
* The customer places an order in Oracle Order Management.
* The system checks stock availability in Oracle Inventory Cloud.
* Since no stock is available, Oracle Supply Chain Orchestration (SCO) triggers a supply request.
* Oracle Global Order Promising (GOP) determines that the item must be manufactured.
* The sales order is scheduled for back-to-back fulfillment.
# System Action: The system marks the sales order for manufacturing and creates a supply order.
Step 2: Create & Request Work Order
* Oracle Supply Chain Orchestration (SCO) generates a Supply Order.
* The system determines that a Work Order (WO) is needed.
* A Work Order (WO) is created in Oracle Manufacturing Cloud.
* The Work Order is tied to the sales order to ensure the finished goods are allocated for this order only.
# System Action: The system creates a Work Order (WO) in Oracle Manufacturing.
Step 3: Execute Manufacturing Process
* The Work Order goes through the standard production process.
* Raw materials are issued from inventory.
* Production activities are completed.
* The final product is reported as complete in Oracle Manufacturing Cloud.
* The Work Order is completed, and the finished goods are transferred to Oracle Inventory Cloud.
# System Action: The system marks the Work Order as complete and updates inventory.
Step 4: Reserve & Ship the Sales Order
* The system reserves the manufactured stock against the sales order.
* The order is picked, packed, and shipped from the warehouse.
* Oracle Shipping Execution updates the order status.
* An invoice is generated in Oracle Receivables.
* The sales order is closed.
# Final Action: The system completes the order and ships it to the customer.
Oracle Fusion Cloud Modules Involved in Make Flow
A screenshot of a computer AI-generated content may be incorrect.
NEW QUESTION # 54
Which two parameters affect the changes you can perform on an interorganization transfer order?
- A. User performing change
- B. Supply source
- C. Receipt routing
- D. Destination type
Answer: A,D
NEW QUESTION # 55
Which three statements are true regarding material status control?
You can change the material status at the time the items are received. (*)
- A. The default lot status can be assigned to an item in item master. (*)
- B. The Material Status Enforced profile option must be set to Yes to enable material status control. (*)
- C. If you do not enable material status control for a transaction type, the transaction type is always disallowed.
- D. The transaction type for which you enable status control defaults as disallowed transaction type for new material statuses that you create.
Answer: A,C
NEW QUESTION # 56
What happens when Transfer Order Required is not enabled in the Manage Interorganization Parameters page for Direct Organization Transfer?
- A. Transfer orders can be created, but approval is mandatory.
- B. Transfer orders cannot be created.
- C. Both interorganization transfers and transfer orders can be created. (*)
- D. Transfer orders cannot be created only from inventory.
Answer: C
NEW QUESTION # 57
While performing a physical inventory count, you find that tags have not been generated for some of the items.
What action is recommended?
- A. Create dynamic tags.
- B. Record these items on existing tags.
- C. Rerun the Generate Physical Inventory Tag process for these items.
Answer: A
NEW QUESTION # 58
Which statement is true when you use kit items on a transfer order?
- A. Only component-level picking is possible.
- B. Component-level picking, shipping, and receiving are possible.
- C. Shipment Set Behavior is not applicable for kit items.
Answer: B
NEW QUESTION # 59
What is the role of a division in an enterprise structure?
- A. It owns the assets of an enterprise.
- B. It defines the destination of an expense.
- C. It represents the primary organizing principle of an enterprise.
Answer: C
NEW QUESTION # 60
Which two statements are true about enterprise structures?
- A. Divisions can be represented in the chart of accounts.
- B. An inventory organization can have more than one cost organization.
- C. Client business units can be part of other legal entities in a shared service center model.
- D. A business unit can be assigned to multiple primary ledgers.
Answer: A,C
NEW QUESTION # 61
Against a Purchase Order quantity of 100, your receiving agent has received 50 items in the receiving type subinventory. Later in the day, 25 items have been put away to inventory. What is the item availability in the Manage Item Quantity UI?
- A. On-Hand: 25, Receiving: 50, Inbound: 50
- B. On-Hand: 25, Receiving: 25, Inbound: 0
- C. On-Hand: 25, Receiving: 25, Inbound: 50 (*)
- D. On-Hand: 50, Receiving: 50, Inbound: 0
Answer: C