NEW QUESTION # 31
Aitchandness inc, manufactures safety footwear and other items of personal protective equipment (PPE). The organisation applied for ISO 45001 certification, and after the initial certificate audit, the certificate body decided that the audit team leader should carry out a follow-up audit to determine whether the non- conformities could be closed out.
A major non-conformity was raised at Stage 2 because of inadequate storage and handling of chemical used in the production process. Minor non-conformities related to retaining documentation, staff safety training and inadequate testing of emergency procedures.
Select four of the actions which the auditor could take at the follow-up audit to determine the effectiveness of corrective action for the non-conformities.
- A. Check whether documented procedures for the revised processes have been signed off by the OH&S Manager.
- B. Check that the safety data sheets associated with the chemical being used where checked for completeness.
- C. Ask whether the organization's internal audit schedule was revised to included more audit associated with the storage and handling of chemicals.
- D. Interview the OH&S Manager to determine whether additional health and safety objectives have been established.
- E. Ask to review the latest emergency response drill report to check whether the revised emergency response process is fit for purpose
- F. Determine whether an updated risk assessment has been carried out on the revised chemical storage and handling processes.
- G. Interview staff to see whether they have received training in the revised emergency response procedures.
- H. Inspect the relevant areas to check whether chemical were being stored and handled in a safe manner.
Answer: A,E,F,H
Explanation:
Follow-up audits verify that corrective actions have been implemented effectively and address the root cause of the nonconformities.
Analysis of Options:
* A. Review the latest emergency response drill report:Correct. This verifies whether emergency response processes are functional and effective.
* B. Check if the internal audit schedule was revised:Incorrect. While beneficial, this is not directly related to closing out the nonconformity.
* C. Check safety data sheets for completeness:Incorrect. While this ensures compliance, it is not directly related to verifying corrective actions.
* D. Check if revised procedures were signed off:Correct. This confirms that changes were properly documented and approved.
* E. Determine whether an updated risk assessment was carried out:Correct. Risk assessments confirm the effectiveness of new controls.
* F. Inspect areas for safe chemical storage and handling:Correct. Direct observation ensures that corrective actions are implemented effectively.
* G. Interview staff on revised emergency procedures:Incorrect. While important, this does not directly address the effectiveness of corrective actions for chemical storage.
* H. Interview the OH&S Manager about additional objectives:Incorrect. This is unrelated to the specific nonconformities raised.
ISO References:
* Clause 10.2.2: Verification of corrective actions.
* Clause 8.1.2: Hazard identification and controls.
NEW QUESTION # 32
An auditor of a manufacturer of plastic packaging products for the food industry found a nonconformity in an internal audit report raised against section 10.2 of ISO 45001 in Report IA202. The nonconformity (NC3) stated: "The level of reported health and safety incidents has increased by 9.7% over the last 12 months. This included an increase in reported accidents." Against this background, the third-party audit team found more than twenty minor nonconformities during the audit, which they agreed should be combined into one major nonconformity against clause 4.4 of ISO 45001. "The organisation has failed to demonstrate that it is maintaining and continually improving a health and safety management system." Select two options which would represent acceptable corrective actions for the nonconformity.
- A. Top management initiated a comprehensive review of the internal and external issues to decide on actions that could lead to improving the performance of the OHSMS.
- B. External consultants were appointed to conduct a gap analysis of the OHSMS and report on the gaps found.
- C. Union representatives of the workers were invited to attend the OH&S management meetings.
- D. Top Management developed and is leading a programme to promote an effective culture of support for the OHSMS.
- E. OH&S champions were appointed in each department to report near misses and incidents in the OHSMS.
- F. Staff from departments with nonconformities were given regular OH&S safety training sessions during their daily toolbox talks.
Answer: A,D
Explanation:
Clause 4.4 of ISO 45001 requires organizations to establish, implement, maintain, and continually improve an OH&S management system. The corrective actions must address systemic issues, involve leadership commitment, and aim to foster a strong safety culture.
Analysis of Options:
A . Top management initiated a comprehensive review of internal and external issues:
Correct. A review of internal and external issues aligns with Clause 4.1 and demonstrates leadership commitment.
B . Union representatives were invited to attend OH&S management meetings:
Incorrect. While participation is valuable, it is not a systemic corrective action.
C . Top management developed and is leading a programme to promote an effective culture of support:
Correct. Promoting a safety culture is a proactive measure and aligns with Clause 5.1 (Leadership).
D . Staff from departments with nonconformities received regular safety training during toolbox talks:
Incorrect. While training addresses specific gaps, it does not address systemic issues.
E . External consultants conducted a gap analysis of the OHSMS:
Incorrect. While helpful, this action does not demonstrate leadership or address systemic improvement.
F . OH&S champions were appointed in each department to report near misses and incidents:
Incorrect. This is a good practice but does not directly address Clause 4.4's requirement for systemic improvement.
ISO Reference:
Clause 4.4: Maintaining and improving the OH&S management system.
Clause 5.1: Leadership and commitment.
Clause 10.3: Continual improvement.
NEW QUESTION # 33
Select the two options which represent an advantage of using a sampling plan for the audit.
- A. Implements the audit plan efficiently
- B. Gives confidence in the audit results
- C. Use of the plan for consecutive audits without review
- D. May miss key issues
- E. May require an increased audit duration
- F. Overrules the auditor's instincts
Answer: A,B
NEW QUESTION # 34
You identify that the OSHMS manager conducts a safety inspection of the building each day before the museum opens to the public. You review your latest report and note that there seems to be some confusion between what constitutes a hazard and what constitutes a risk.
Which three of the following observations has the OHSMS manager correctly rated?
- A. Conference room emergency sign directs people to an exit that is no longer available for use (Hazard)
- B. The fire extinguishers in the Natural World area have not been serviced in the last five years [Risk)
- C. The emergency light In the gift shop did not work when checked (Risk)
- D. The non-slip mats have been removed from the restaurant (Risk)
- E. There Is a high possibility of unfit food being sold due to the failure of the oven temperature indicator In the visitors' restaurant (Hazard)
- F. The head of the dinosaur suspended over the main hall has become detached from the rest of the skeleton (Risk)
- G. The carpet on the main staircase is peeling off (Risk)
- H. There is a water leak next to the electric heater in the admissions area (Danger)
Answer: B,C,G
Explanation:
Comprehensive Detailed Explanation along with All ISO 45001 Audit Reference Hazard: A potential source of harm or adverse health effects.
Risk: The likelihood of harm occurring as a result of the hazard.
Danger: An immediate threat that requires urgent action.
Analysis of Options:
A . Conference room emergency sign directs people to an exit that is no longer available for use (Hazard):
Correctly identified as a hazard since it poses a potential risk during emergencies.
B . The carpet on the main staircase is peeling off (Risk):
This is a hazard, not a risk, as it represents a source of potential harm.
C . The emergency light in the gift shop did not work when checked (Risk):
This is a hazard because it is a condition that could lead to a risk during emergencies.
D . The fire extinguishers in the Natural World area have not been serviced in the last five years (Risk):
Correctly identified as a risk because the likelihood of fire-related harm increases without proper servicing.
E . The head of the dinosaur suspended over the main hall has become detached from the rest of the skeleton (Risk):
This is a hazard, not a risk, as it represents a potential source of harm.
F . The non-slip mats have been removed from the restaurant (Risk):
This is a hazard, not a risk.
G . There is a high possibility of unfit food being sold due to the failure of the oven temperature indicator in the visitors' restaurant (Hazard):
This is a risk because it specifies the likelihood of harm occurring (selling unfit food).
H . There is a water leak next to the electric heater in the admissions area (Danger):
Correctly identified as a danger because it represents an immediate and critical threat.
ISO Reference:
Clause 6.1.2: Hazard identification and assessment of risks and opportunities.
NEW QUESTION # 35
Out of the following, which is not the Part of PDCA cycle of ISO 45001? Select the correct option, and then select Submit.
- A. OHSMS Policy
- B. Environment Management Program
- C. Analyzing OHSMS Performance Submit
- D. Treatment of Risks
Answer: B
Explanation:
The PDCA (Plan-Do-Check-Act) cycle is a core principle of ISO 45001 and many other management systems. It does not include environmental management, as ISO 45001 focuses on Occupational Health & Safety (OH&S), while environmental aspects are covered by ISO 14001.
Analysis of Options:
* A. Treatment of Risks:Correct. Risk assessment and control are part of the Plan phase.
* B. OHSMS Policy:Correct. The OH&S policy is established in the Plan phase.
* C. Environment Management Program:Incorrect. This is outside the scope of ISO 45001 and pertains to ISO 14001.
* D. Analyzing OHSMS Performance:Correct. Performance analysis occurs in the Check phase of the PDCA cycle.
ISO Reference:
* Clause 0.3: PDCA model in ISO 45001.
NEW QUESTION # 36
Wokrer's participations is a key factor for the success of OHSMS. Which three of the following ISO 45001 activities require workers' participation?
- A. Determining actions to eliminate hazards
- B. Establishing OHS objectives
- C. Determining competence requirements
- D. Establishing OHS policy
- E. Determining what needs to be communciated
- F. Managing internal audit programme
Answer: A,B,D
Explanation:
Worker participation is a fundamental principle of ISO 45001 (Clause 5.4). It ensures workers at all levels are involved in key activities to enhance the OH&S management system's effectiveness.
Analysis of Options:
* A. Determining competence requirements:Incorrect. Determining competence is primarily the responsibility of management, though workers may provide input.
* B. Establishing OHS objectives:Correct. Worker involvement ensures objectives are realistic and relevant to workplace conditions (Clause 6.2).
* C. Managing internal audit programme:Incorrect. Managing audits is typically a managerial responsibility, though workers may participate in audits.
* D. Determining actions to eliminate hazards:Correct. Workers' insights are critical in identifying and implementing actions to eliminate hazards (Clause 8.1.2).
* E. Determining what needs to be communicated:Incorrect. While communication strategies impact workers, their participation in determining communication needs is not explicitly required.
* F. Establishing OHS policy:Correct. Workers should be involved in developing policies to ensure relevance and buy-in (Clause 5.2).
ISO References:
* Clause 5.4: Worker participation.
* Clause 6.2: OHS objectives.
* Clause 8.1.2: Hierarchy of controls and hazard elimination.
NEW QUESTION # 37
Which of the following standards talk about the Environment Management System? Select all the correct options, and then select Submit.
- A. ISO 14501
- B. ISO 14001
- C. ISO 45001
- D. Integrated Management system
Answer: B,D
Explanation:
Analysis of Options:
A . Integrated Management System:
Correct. An Integrated Management System (IMS) combines multiple standards like ISO 45001, ISO 14001, and ISO 9001, addressing environment management as part of the integration.
B . ISO 14501:
Incorrect. ISO 14501 pertains to milk and milk products, not environmental management.
C . ISO 45001:
Incorrect. ISO 45001 focuses on Occupational Health and Safety, not environmental management.
D . ISO 14001:
Correct. ISO 14001 is the primary standard for Environmental Management Systems.
ISO Reference:
ISO 14001: Environment Management Systems.
Integrated Management Systems: Combines standards like ISO 14001 and ISO 45001.
NEW QUESTION # 38
An audit team leader prepares the audit plan for an initial Stage 2 certification audit. Which two of the following statements are false?
- A. The audit team leader should present the plan to the auditee before the Stage 2 audit.
- B. The plan does not need to include the names of the senior managers.
- C. The organisation should review the audit plan for agreement.
- D. The organisation should cancel at staff leave during the audit.
- E. The audit team leader should plan to interview each employee.
- F. The audit team leader does not select the OHS audit team members.
Answer: E,F
Explanation:
Comprehensive Detailed Explanation along with All ISO 45001 Audit Reference Analysis of Each Option:
A . The organisation should review the audit plan for agreement.
True.
According to ISO 45001 guidelines and ISO 19011 (Guidelines for Auditing Management Systems), it is standard practice for the auditee organization to review and agree to the audit plan to ensure clarity on scope, objectives, and processes.
Reference: ISO 19011:2018, Clause 6.3.2.
B . The audit team leader does not select the OHS audit team members.
False.
The audit team leader is responsible for selecting competent team members with the requisite expertise to evaluate the auditee's Occupational Health & Safety Management System (OHSMS). Selection is based on criteria such as knowledge of ISO 45001, auditing skills, and understanding of the industry.
Reference: ISO 19011:2018, Clause 5.4.2 and 6.3.1.
C . The audit team leader should plan to interview each employee.
False.
While employee interviews are an essential part of gathering evidence during an ISO 45001 audit, interviewing every employee is impractical and unnecessary. A representative sampling strategy is used to assess compliance across various levels and departments.
Reference: ISO 19011:2018, Clause 6.4.6.
D . The audit team leader should present the plan to the auditee before the Stage 2 audit.
True.
Presenting the audit plan to the auditee before the audit is essential to ensure all parties are informed and prepared for the audit. This practice is emphasized in ISO 19011 and supports transparency and effective audit execution.
Reference: ISO 19011:2018, Clause 6.3.3.
E . The organisation should cancel staff leave during the audit.
False.
ISO 45001 and related audit guidelines do not mandate the cancellation of staff leave during audits. While key personnel should be available, the audit team collaborates with the organization to plan around leave schedules to minimize disruption.
Reference: Not explicitly covered in ISO 45001 or ISO 19011; falls under planning discretion.
F . The plan does not need to include the names of the senior managers.
True.
While the audit plan should outline the scope, objectives, and methods, it does not specifically require the inclusion of senior managers' names unless they are directly involved in the audit.
Reference: ISO 19011:2018, Clause 6.3.2.
Key ISO Reference:
ISO 45001:2018, Clause 9.2 (Internal Audit Requirements).
ISO 19011:2018, Clauses 5.4.2, 6.3.1, 6.3.2, and 6.4.6.
NEW QUESTION # 39
You are auditing a site of Good Food Shack, a restaurant chain. In the kitchen area, you notice a half-filled open drum sitting in a pool of liquid, which is dribbling across a work area. You ask the head Chef what is in the drum and are told it is waste the frying process. When you ask why it is kept there, You are told that it is not normally kept there, but it not a problem and says that he will arrange it to be moved to a storeroom and will give the floor a good clean.
Look around the kitchen, you observe knives and cleavers lying around on worktops, staff wearing no protective gloves and a large pot of boiling water with nobody near it. There is no evidence of any fire extinguishers of fine blankets within sight.
You decide to raise a nonconformance. Select one of the options that best describes the finding against clause
8.1.2 of ISO 45001.
- A. Training of the kitchen staff was not effective enough to prevent poor safety awareness in the kitchen area.
- B. Staff are at risk of serious injury while working in the kitchen.
- C. Measures to prevent slippage in the kitchen from waste cooking oil were not taken.
- D. Failure to reduce risks associated with working in the kitchen.
Answer: D
Explanation:
Comprehensive Detailed Explanation along with All ISO 45001 Audit References Clause 8.1.2 of ISO 45001 pertains to Eliminating Hazards and Reducing OH&S Risks. Organizations must implement appropriate controls to manage workplace hazards effectively.
* Issue Identified:The kitchen environment at the audited site presents multiple hazards, including:
* Oil spillage creating a slip hazard.
* Open drums of waste material posing a chemical or hygiene hazard.
* Unsecured knives and cleavers increasing the risk of cuts.
* Boiling water left unattended, posing a risk of burns.
* Lack of visible fire extinguishers or fire blankets, increasing fire risk.
* Analysis of Options:
* A. Failure to reduce risks associated with working in the kitchen.This option accurately captures the broader failure to implement effective measures to eliminate or reduce hazards across multiple areas in the kitchen.
* B. Measures to prevent slippage in the kitchen from waste cooking oil were not taken.This is specific to one hazard (oil spillage) and does not address other significant risks observed, such as fire safety or sharp tools.
* C. Staff are at risk of serious injury while working in the kitchen.While true, this is more of a general observation and does not address the root cause of the hazards or the failure of controls.
* D. Training of the kitchen staff was not effective enough to prevent poor safety awareness in the kitchen area.Although training deficiencies may contribute to the issue, this option does not reflect the overarching systemic failure to manage hazards effectively.
* Best Description of the Nonconformance:Failure to reduce risks associated with working in the kitchen (Option A) is the most comprehensive finding, reflecting the organization's lack of adequate controls to mitigate hazards.
ISO References:
* Clause 8.1.2: Organizations must establish controls to eliminate or minimize OH&S risks systematically.
* Clause 7.2: Ensuring competency through training is important but must be coupled with hazard control measures.
NEW QUESTION # 40
On behalf of a certification body, you are conducting a combined audit of Shelf-Fit. The organization designs, manufacturing install interiors for retail stores. They employ subcontractors for the installation work.
Representing the ISO 45001 audit, you ask the Purchase Manager about the identification of health and safety hazards for contractors on site. Having previously reviewed the hazards list (HZD-21/11 Rev.3), you found that various health and safety hazards were listed but not were associated with contractor working on-site.
When you ask about the use of contractors, the response is, ''We know that contractors use chemicals, such as glues, paints and vanishes. We trust them since they know more than we do about the safe handling of such issues''. The auditor made the same enquiry to an accompanying member of the health and safety team and was told that chemical safety had never been a problem with the installation process.
- A. There was not communication between the organization and site contractors (7.4.1.c.2)
- B. After gathering more evidence, you note down findings against several clauses of ISO 45001. Select three options to determine which findings stated are major nonconformities.
- C. The organization failed to include its OH&S policy in contracts for installation contractors (5.2.f)
- D. The purchase manager confirmed that the safe use of chemicals in installation work was left to the contractor
- E. The organization did not have a documented process in place to control outsourced work. (8.1.4.3)
- F. No hazard assessment by Shelf-Fit were in place for installation works on customer sites. (Clause 6.1.2.2)
- G. Some safety data sheets for chemical used were missing for some of the installation contractors.(clause 8.1.4.2)
- H. The internal audit programme does not include installation sites. The audit programme does not cover the full OHS management system (Clause 9.2.2)
- I. Staff indicated that chemical hazards on installation sites are the same as at the factory. The hazard List does not reference this. (Clause 6.1.2.2)
Answer: A,E,I
Explanation:
Major nonconformities are raised when there is a systemic failure to meet ISO 45001 requirements that could lead to significant risks.
Analysis of Options:
B . Lack of a documented process for controlling outsourced work (8.1.4.3):
Major nonconformity. A failure to control outsourced work is a serious systemic issue.
C . Failure to include OH&S policy in contractor contracts (5.2.f):
Not a major nonconformity. While this is a nonconformity, it is procedural and not critical.
D . No hazard assessment for installation works (6.1.2.2):
Major nonconformity. A lack of hazard assessment for site-specific tasks is a serious issue.
E . Missing safety data sheets for contractor chemicals (8.1.4.2):
Not a major nonconformity. While important, this issue does not indicate systemic failure.
G . Chemical hazards on installation sites not referenced in the hazard list (6.1.2.2):
Major nonconformity. This reflects a failure in hazard identification and risk assessment.
H . Internal audit program does not cover installation sites (9.2.2):
Not a major nonconformity. This is a gap in auditing scope but does not directly endanger safety.
I . Safe use of chemicals left to contractors:
Not a major nonconformity. This could be addressed through improved contractor oversight rather than indicating systemic failure.
ISO Reference:
Clause 8.1.4.3: Control of outsourced processes.
Clause 6.1.2.2: Hazard identification and risk assessment.
Clause 7.4.1: Communication requirements.
NEW QUESTION # 41
A well-known fast-food organisation (ISO 45001 certified) contracts young people to deliver orders; last week one of them died in a street accident riding for the first time a new motorbike provided by the organisation. You will lead the recertification audit in two weeks, and you plan to prepare a checklist to investigate this incident. The following are potential questions you might ask; match them to the related ISO 45001 clause/subclause.
Answer:
Explanation:
NEW QUESTION # 42
Wash-it-up is an organization that provides window cleaning services for the industrial sector. It has been certified t ISO 45001 for some time and has appointed a new OHS Manager. The audit plan during a surveillance audit includes the improvement actions and the auditor asks to see the most recent management review meeting minutes.
surveillance audit includes the Improvement actions and the auditor asks to see the most recent management review meeting minutes.
Which six of the statements would represent output audit evidence for the management review?
- A. Minutes of previous management reviews
- B. Allocation of a bigger budget for the OHS department
- C. Worker feedback of positive and negative comments
- D. Updates to the risk register
- E. Procurement of new safety harnesses for workers
- F. Report showing the trend of an increase In safety incidents
- G. Decagons related to continual improvement opportunities
- H. Improvements In the OHSMS
- I. Opportunities to integrate the OHS management system with other business processes
- J. Plan to priorities health and safety issues as a business strategy
Answer: B,D,G,H,I,J
Explanation:
Comprehensive Detailed Explanation along with All ISO 45001 Audit Reference Clause 9.3 of ISO 45001:2018 outlines the requirements for management reviews. These reviews must evaluate the performance of the OHSMS and identify opportunities for improvement. Outputs of management reviews typically include decisions and actions that align with strategic and operational priorities.
Analysis of Options:
A . Decisions related to continual improvement opportunities:
This is a valid output, as continual improvement is a key objective of management reviews under Clause 10.3.
B . Allocation of a bigger budget for the OHS department:
Resource allocation is a common output of management reviews to address identified needs.
C . Improvements in the OHSMS:
Improvements reflect the organization's commitment to enhancing safety performance.
D . Minutes of previous management reviews:
While minutes provide context, they are not an output of the current management review.
E . Opportunities to integrate the OHS management system with other business processes:
Integration opportunities are valid outputs, as they enhance the system's effectiveness.
F . Plan to prioritize health and safety issues as a business strategy:
Strategic alignment of health and safety with business objectives is an expected output.
G . Procurement of new safety harnesses for workers:
This is an operational action, not a direct output of the management review process.
H . Report showing the trend of an increase in safety incidents:
This is an input to the management review, not an output.
I . Updates to the risk register:
Risk register updates reflect changes in identified hazards and risks, making this a valid output.
J . Worker feedback of positive and negative comments:
Worker feedback is an input to the management review, not an output.
ISO Reference:
Clause 9.3: Management review inputs and outputs.
Clause 10.3: Continual improvement actions.
NEW QUESTION # 43
An audit team leader arrives at a fabrication organisation that manufactures stairways to ..certification audit.
At a meeting with the OHSMS Manager the audit finds that the responsibility for worker consultation and participation lies with the managerial team. Select from the options four actions by the managerial team that encourage worker consultation and participation.
- A. threatening reprisals to whistleblowers
- B. Ignoring worker's suggestions
- C. Implementing methods tor engaging workers
- D. Giving ownership of health and safety matters
- E. Promoting collaborating workers to higher positions
- F. Implementing a payment scheme to reward worker's OHS performance
- G. Appointing worker's representatives
- H. Conducting toolbox talks on health and safety
Answer: C,D,G,H
Explanation:
Comprehensive Detailed Explanation along with All ISO 45001 Audit References Clause 5.4 of ISO 45001:2018 emphasizes the importance of worker consultation and participation in the OHS management system. It requires organizations to establish processes that ensure workers are actively involved in decision-making and implementation of OHS practices.
Analysis of Options:
* A. Promoting collaborating workers to higher positions:While promotions may boost morale, they do not directly contribute to worker consultation and participation in the OHSMS.
* B. Appointing worker representatives:This action fosters direct communication and representation of workers' interests in health and safety matters.
* C. Conducting toolbox talks on health and safety:Toolbox talks are an effective way to engage workers in discussing and addressing health and safety issues.
* D. Giving ownership of health and safety matters:Involving workers in decision-making and giving them responsibility for specific health and safety tasks encourages participation.
* E. Ignoring workers' suggestions:This undermines consultation and is contrary to ISO 45001 principles.
* F. Implementing a payment scheme to reward workers' OHS performance:While incentives can motivate safe behavior, they are not a consultation or participation mechanism as required by Clause
5.4.
* G. Implementing methods for engaging workers:This aligns directly with Clause 5.4, as effective engagement methods (e.g., surveys, focus groups) enhance participation.
* H. Threatening reprisals to whistleblowers:This violates ISO 45001 principles and discourages worker participation.
ISO References:
* Clause 5.4: Worker consultation and participation.
* Clause 5.1: Leadership's responsibility to foster participation.
NEW QUESTION # 44
Which two of the following are 'criteria' in relation to a first-party audit?
- A. Management policy
- B. Workers complaints"
- C. Duration of the audit
- D. Emergency plans
- E. Opportunities for improvement
- F. Members of the audit team
Answer: A,D
NEW QUESTION # 45
What is the definition of the term 'audit' as per clause 3.32 of ISO 45001:2018?
- A. A document that outlines safety procedures and guidelines
- B. A legal requirement to comply with health and safety standards
- C. An evaluation of the effectiveness of health and safety measures
- D. A systematic process to assess the risks in a workplace
Answer: C
Explanation:
According to Clause 3.32 of ISO 45001:2018, an audit is defined as a systematic, independent, and documented process for obtaining objective evidence and evaluating it to determine the extent to which audit criteria are fulfilled.
This involves assessing the effectiveness of health and safety measures implemented in the organization's OH&S management system.
Analysis of Options:
* A. A systematic process to assess the risks in a workplace:Incorrect. While audits may include risk assessments, the purpose is broader and involves evaluating the entire OH&S management system.
* B. An evaluation of the effectiveness of health and safety measures:Correct. This aligns with the definition of an audit as per ISO 45001:2018.
* C. A legal requirement to comply with health and safety standards:Incorrect. An audit is not necessarily a legal requirement but a process to assess conformity.
* D. A document that outlines safety procedures and guidelines:Incorrect. An audit is a process, not a document.
ISO Reference:
* Clause 3.32: Audit definition.
NEW QUESTION # 46
During a second-party audit at a sawmill, you find that the OHSMS Manager conducted the hazard identification process. In the risk assessment report, hazards were listed as physical hazards, chemical hazards, biological hazards, and psychosocial hazards, with the hazards categorized as low, medium, and high risk to be addressed. The OHSMS Manager did not have an action plan for low and medium risks, saying that they ignored those. He stated that they brought in a health and safety consultant to advise on treatment for the high risks.
When interviewing the OHSMS Manager, the auditor presents a nonconformity relating to potential hazards in the factory if the dust extraction system broke down. The OHSMS Manager said that, if that happened, the agreed planned action is that workers would put masks on.
Select one of the options for how the auditor should respond to this statement.
- A. Ask the OHSMS Manager to confirm that this action meets regulatory requirements for air purity.
- B. Seek evidence that the response action is both implemented and effective.
- C. Advise that the factory should cease its operations if the dust extraction equipment malfunctioned.
- D. Suggest that they should increase their maintenance checks.
Answer: B
NEW QUESTION # 47
......
PECB ISO-45001-Lead-Auditor Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
Download Real PECB ISO-45001-Lead-Auditor Exam Dumps Test Engine Exam Questions: https://vcetorrent.passreview.com/ISO-45001-Lead-Auditor-exam-questions.html