The SAP C_ACTIVATE13 Certification Exam is a subjective exam. Therefore, the candidate must meet the prerequisites set by the organization. The candidate must be enrolled in the certification program and have passed the prerequisites set by the organization. The premium question bank, like C_ACTIVATE13 Dumps, will be available for the prep of the exam, and the candidate must have access to these guides. The candidate must have an active SAP Activate account and must have a valid email address. The candidate must have a good understanding of the SAP Activate methodology.
NEW QUESTION 26
Identify the two landscape transformation specific tasks in the explore phase.
There are 2 correct answers to this question.
Response:
- A. Perform Client transfer
- B. Run a Landscape Transformation Assessment
- C. Setup Landscape Transformation Software
- D. Define the Data Migration Architecture
Answer: B,C
NEW QUESTION 27
In which SAP Activate methodology phase does the team complete the Transformation Strategy?
Please choose the correct answer.
Response:
- A. Realize
- B. Prepare
- C. Explore
- D. Deploy
Answer: B
NEW QUESTION 28
What tool is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks?
Please choose the correct answer.
Response:
- A. SAP Code Inspector
- B. Retrofit
- C. Business Process Change Analyzer
- D. SAP Code Vulnerability Analyzer
Answer: B
NEW QUESTION 29
What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the "System Conversion" transition path?
Please choose the correct answer.
Response:
- A. SAP Code Inspector
- B. Simplification Item Check (SI-Check)
- C. Software Provisioning Manager
- D. Software Update Manager with Database Migration Option
Answer: B
NEW QUESTION 30
What are the benefits of the SAP best practices?
There are 3 correct answers to this question.
Response:
- A. Fixed organizational structure
- B. Reduced functional scope
- C. Fast time to value
- D. Predictable results
- E. Simple on-boarding to cloud
Answer: C,D,E
NEW QUESTION 31
What is the term used for workshops, which are intended to set value targets, Validate SAP standard.
- A. Fit-to-standard
- B. Design thinking
- C. Solution validation
- D. Delta design
Answer: C
NEW QUESTION 32
What sprint types are part of the SAP activate methodology There are 3 correct answers to this question.
- A. Initial
- B. Foundational
- C. Build
- D. Firm-up
- E. Daily
Answer: B,C,D
NEW QUESTION 33
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration?
Please choose the correct answer.
Response:
- A. To create delta building blocks for complementary content
- B. To activate the Best Practices content
- C. To personalize activated, ready-to run business processes
- D. To create customer-specific scope items
Answer: B
NEW QUESTION 34
Preliminary strategy developed by the customer to approach the project in a specific workstream
- A. Project result that is developed solely by the partner
- B. Preliminary strategy developed by the customer to approach the project in a specific workstream
- C. Approach document that is developed by a united project team (partner+ customer)
- D. Optional information that is NOT important for project activities
Answer: B
NEW QUESTION 35
What is the difference between the "System Conversion and the "New Implementation of SAP S/4HANA" transition paths?
There are 2 correct answers to this question.
Response:
- A. In the Realize phase, data is converted and NOT migrated for System Conversion.
- B. There are different upgrade cycles.
- C. In the Realize phase, custom code is adjusted rather than developed for System Conversion.
- D. SSCUls are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app.
Answer: A,C
NEW QUESTION 36
Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:
- A. Expert Configuration
- B. SAP Solution Composer
- C. Self Service Configuration
- D. Solution Builder
- E. Model Company
Answer: A,C,D
NEW QUESTION 37
Which of the following tasks are required in the Prepare Phase?
There are 3 correct answers to this question.
Response:
- A. Approve the test strategy
- B. Define the communication plan
- C. Train the project team
- D. Set up the infrastructure to support the project
- E. Identify relevant SAP Best Practices
Answer: C,D,E
NEW QUESTION 38
Which statement are part of the 5 golden rules for SAP S/4HANA Cloud single tenant edition?
There are 2 correct answers to this question.
- A. Document deviations from golden rules for transparency and future use in upgrade
- B. Foster cloud mindset and adherence to the fit to standard approach
- C. Use SAP solution manager 7.2 with focused build
- D. Stick to the security standard of the customer organisation
Answer: A,B
NEW QUESTION 39
Which new role is introduced in the SAP activate methodology in a full scrum team?
- A. Project manager
- B. Application consultant
- C. System administrator
- D. Product owner
Answer: B
NEW QUESTION 40
Which of the following tools are specific to the Data Management work stream? Note: There are 3 correct answers to this question
- A. SAP Landscape Transformation
- B. SAP Solution Manager
- C. SAP Data Services
- D. SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions)
- E. SAP Roadmap Viewer
Answer: B,C,D
NEW QUESTION 41
The tasks associated with Landscape transportation are in which workstream?
Please choose the correct answer.
Response:
- A. Technical Architecture and Infrastructure
- B. Application Solution Adoption
- C. System & Data Migration
- D. Transition to Operations
Answer: C
NEW QUESTION 42
What are the responsibilities of the Product Owner in release and sprint planning?
There are 2 correct answers to this question.
Response:
- A. Estimate the backlog user stories.
- B. Prioritize backlog user stories by business priority.
- C. Define objectives for each release.
- D. Analyze the functional and technical dependencies between the user stories.
Answer: B,C
NEW QUESTION 43
Which of the following SAP S/4HANA Landscape Transformation options are enabled?
There are 3 correct answers to this question.
Response:
- A. Migration of Business Units
- B. Security Migration
- C. System Consolidation
- D. System Upgrade
- E. Migration of Selected Applications
Answer: A,C,E
NEW QUESTION 44
Which activities are critical for delivering Agile projects?
There are 2 correct answers to this question.
Response:
- A. Retrospective agenda creation
- B. Sprint planning
- C. Blueprint scheduling
- D. Release planning
Answer: B,D
NEW QUESTION 45
What technique helps a scrum team to prioritize a large, flat backlog?
- A. Fit/gap analysis
- B. Planning poker
- C. User story mapping
- D. Retrospective
Answer: C
NEW QUESTION 46
In which phase should you create a data migration strategy (LO) during a selective data transition?
- A. Explore
- B. Discover
- C. Realise
- D. Deploy
Answer: B
NEW QUESTION 47
What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the "System Conversion" transition path?
- A. SAP Code Inspector
- B. Software Provisioning Manager
- C. Software Update Manager with Database Migration Option
- D. Simplification Item Check (Si-Check)
Answer: D
NEW QUESTION 48
......